Project: Uganda Medicinal Cannabis Development

Baseline Objectives - 90-Day Plan

This project provides a governance and project-development framework for exploring the potential of a medicinal cannabis industry and associated investment in Uganda. The initiative arises from discussions concerning the potential for medicinal cannabis to contribute to economic development, healthcare-related activity, employment, skills and investment, while recognising the risks associated with poorly governed development, external investment and insufficient local participation. The project does not begin from the assumption that medicinal cannabis development, any particular investment model, or any particular organisation represents the correct solution. Instead, it establishes a structured environment in which the proposition can be progressively defined, challenged and supported by evidence. Project Health Control (PHC) will initially provide the governance structure through which project information, stakeholder concerns, evidence, actions, deliverables, decisions and funding-readiness can be developed and made traceable. Draft status: This initial project definition has been prepared from preliminary discussions and is intended for review, correction and development with relevant Ugandan stakeholders and other participants.

πŸ“„ The Story of PHC
Overall: Executive Summary

This 90-day plan mobilises the lean Project Health Control (PHC) foundation for Uganda Medicinal Cannabis Development. It covers the seven-day Verification Preview in Month 1 and the two-month Foundation Setup in Months 2 and 3.

The plan is designed to turn an early commercial opportunity into a controlled, evidence-led project environment. It will clarify what authority and information exist, organise concerns and actions, establish governance and document control, and define the specialist legal, regulatory, commercial and technical work required for the next decision. It does not authorise cultivation, processing, product supply, investment promotion, hardware procurement or operational launch.

[+] Purpose

Create a credible foundation for deciding whether and how the Ugandan medicinal cannabis opportunity should progress.

  • Confirm the project mandate, sponsor, accountable roles and relationship between PHC, Dr Michelle Nyangereka and the Ugandan Medicinal Cannabis Consortium steering committee.
  • Establish a controlled source of project information, evidence, assumptions, concerns, risks, actions, decisions and Deliverables.
  • Align the Project Information, Commercial Framing Questions, Strategic Plan, Manifesto, Business Case and Proposal.
  • Identify the qualified Ugandan legal, regulatory, commercial, agricultural, healthcare, technical and stakeholder inputs still required.
  • Protect meaningful Ugandan participation and locally retained value as explicit design and decision criteria.

The 90 days should create decision readiness for the next phase, not manufacture certainty or a case for predetermined investment.

[+] What β€œSuccess” Looks Like (by Day 90)

By Day 90, authorised participants should be able to see clearly:

  • who currently sponsors, governs and contributes to the project, including roles or authorities that remain TBD;
  • what is verified, what is an assumption or stakeholder view, and what evidence is still missing;
  • the principal regulatory, commercial, ownership, investment and local-value questions requiring specialist work;
  • the current Concerns, risks, Actions, decisions, Deliverables and evidence status;
  • the proposed definition-phase scope, sequence, resource requirements and decision gates;
  • whether the project should proceed into Definition Oversight, proceed conditionally, be redesigned, pause or stop.

Success does not require the medicinal cannabis opportunity to be approved. A well-evidenced decision not to progress, or not yet to progress, is a valid governance outcome.

Phase 1: Days 1–30 (Stabilise & Baseline)

Days 1-30 establish the truth of the starting position. PHC will complete the seven-day Verification Preview, record what has actually been supplied or confirmed, identify immediate governance and evidence gaps, and issue a Go/No-Go/Conditional-Go recommendation for Foundation Setup. Any remaining time in the first month is used only for authorised clarification and mobilisation preparation.

[+] Objectives

  • Verify the current project narrative, available records, named participants and stated relationship to the Consortium steering committee and White Paper.
  • Distinguish verified facts from assumptions, aspirations, stakeholder views and unknowns.
  • Identify immediate concerns affecting authority, legality, ownership, confidentiality, evidence access and responsible investment.
  • Determine whether the minimum conditions exist for a controlled PHC Foundation Setup.

[+] Actions

  • Opening confirmation: agree the review contact, permission to use supplied material, communication route and intended recipients of the advisory note.
  • Evidence review: inspect available Project Information, Consortium or steering material, White Paper material, stakeholder information and prior decisions.
  • Initial mapping: create preliminary People, Locations, Events, Deliverables, Concerns, Actions, risks, assumptions, decisions and evidence records.
  • Governance check: identify the claimed or actual sponsor, accountable executive, steering authority, legal/project vehicle and PHC mandate, marking each item verified or TBD.
  • Readiness check: assess whether access, participation and information are sufficient to begin Foundation Setup.
  • Advisory: issue a concise Go/No-Go/Conditional-Go note with unresolved conditions and a recommended Days 31-90 scope.

[+] Deliverables by Day 30

  • Verification Preview Advisory Note - recommendation, basis, limitations and conditions for further mobilisation.
  • Current-State Evidence Index v0.1 - material received, source, date, status, permissions and notable gaps.
  • Initial Governance and Stakeholder Map v0.1 - known contacts, claimed roles, authority requiring confirmation and priority engagement needs.
  • Initial Concerns, Actions and Assumptions Set v0.1 - immediate matters requiring ownership or specialist evidence.
  • Foundation Setup Scope v0.1 - proposed boundaries, Deliverables, participants and prerequisites for Days 31-90.

[+] Measures

  • The advisory note is issued with an explicit Go, No-Go or Conditional-Go position.
  • Every material statement reviewed is distinguishable as verified, unverified, assumed, stakeholder-supplied or TBD.
  • Immediate concerns have a named owner or a recorded need for sponsor assignment.
  • The conditions, authority and evidence needed to start Foundation Setup are visible.
  • No regulatory, commercial or investment claim is presented as confirmed without an identified source and appropriate competence.
Phase 2: Days 31–60 (Align & Standardise)

Days 31-60 begin the PHC Foundation Setup. The priority is to create a common control structure, bring the Draft 0.1 document set into alignment and agree how people, evidence and decisions will enter the project. This phase makes the work governable before it attempts to make the commercial proposition look complete.

[+] Objectives

  • Confirm the practical governance, review and information-management arrangements for the definition stage.
  • Create controlled registers and a clear status model for project evidence and decisions.
  • Align the foundation documents around the Commercial project category, responsible investment and Ugandan value retention.
  • Translate broad unknowns into scoped evidence requests and specialist work packages.

[+] Actions

  • Governance design: draft the sponsor, steering, PHC and specialist roles; delegated decisions; conflict declarations; meeting rhythm; and escalation route.
  • PHC configuration: establish the project records, status definitions, ownership fields, links, review dates and document references needed for control.
  • Document alignment: reconcile the Project Information, Framing Questions, Strategic Plan, Manifesto, Business Case, Proposal and this 90-Day Plan.
  • Evidence planning: group gaps into regulatory, legal, market, value-chain, ownership, financial, technical, environmental, social and stakeholder themes.
  • Stakeholder preparation: identify who should validate each area, what authority they hold and how their contribution will be recorded and approved.
  • Cost boundary review: confirm the lean PHC working estimate and list excluded hardware, travel, specialist and operational costs requiring later approval.

[+] Deliverables by Day 60

  • Draft Governance and Decision Map v0.1 - roles, authority, meeting rhythm, conflicts and escalation.
  • PHC Control Registers v0.1 - Concerns, Actions, risks, assumptions, decisions, Deliverables and evidence with initial ownership.
  • Controlled Foundation Document Set v0.1 - aligned status, version and cross-references across the core documents.
  • Evidence Requirements Matrix v0.1 - question, purpose, source, competence required, owner, timing and decision affected.
  • Specialist Work Package List v0.1 - proposed legal, regulatory, commercial and technical inputs for later scoping and cost.

[+] Measures

  • Each core register has an agreed purpose, status convention, owner and review route.
  • Contradictions between foundation documents are either resolved or recorded as open concerns.
  • Material evidence gaps are linked to a decision, proposed source and competence requirement.
  • Roles and authorities are confirmed where possible and explicitly marked TBD where not.
  • PHC Service costs are separated from excluded specialist, hardware and operational costs.
Phase 3: Days 61–90 (Embed & Improve)

Days 61-90 complete the initial Foundation Setup and prepare the handoff into Definition Oversight. The emphasis shifts from configuring controls to using them: reviewing evidence, recording decisions, testing the developing commercial logic and presenting an authorised recommendation for the next phase.

[+] Objectives

  • Demonstrate that the governance and evidence controls work in practice.
  • Convert priority gaps into an ordered definition-stage programme with owners, dependencies and decision gates.
  • Establish the current maturity of the Business Case, Proposal and Funding Readiness position without overstating certainty.
  • Secure an accountable Day 90 decision on the project's next step.

[+] Actions

  • Operate the review rhythm: hold agreed project-health reviews, update registers and record decisions, dissent, conflicts and outstanding Actions.
  • Prioritise evidence: rank regulatory, governance, market, ownership, local-value and commercial questions by decision impact and urgency.
  • Scope next-stage work: define Deliverables, acceptance criteria, dependencies and indicative resource categories for Definition Oversight and specialist support.
  • Test the commercial logic: review whether the proposed opportunity, options and investment logic remain coherent against evidence received.
  • Review funding readiness: identify the conditions that prevent or permit responsible engagement with funders or investors.
  • Prepare the Day 90 gate: present the evidence, unresolved concerns, recommended next step and any conditions for approval.

[+] Deliverables by Day 90

  • 90-Day Project Health Pack - status of governance, scope, evidence, Concerns, Actions, risks, decisions and Deliverables.
  • Definition-Phase Roadmap v0.1 - prioritised work packages, dependencies, proposed owners, acceptance criteria and decision gates.
  • Updated Business Case and Proposal Position - changes required as a result of verified evidence and stakeholder input.
  • Funding Readiness Gap Statement v0.1 - what is established, what remains insufficient and what must happen before external funding engagement.
  • Day 90 Gate Recommendation - proceed to Definition Oversight, proceed conditionally, redesign, pause or stop, with reasons and required authority.

[+] Measures

  • The agreed review and decision process has been used and produces traceable Actions and decisions.
  • Priority evidence gaps have owners, proposed sources, dependencies and target decision points, or are explicitly unassigned/TBD.
  • The developing Business Case separates evidence from assumptions and includes credible alternatives, including pause or stop.
  • The next-phase resource categories and exclusions are visible without inventing unsupported costs.
  • An authorised Day 90 recommendation is recorded with conditions, dissent and unresolved matters.