Project: PHC School Model Uganda

Baseline Objectives - 90-Day Plan

This project will implement the full PHC Service at [school to be selected] Uganda. School leadership, teachers, parents and pupils will be invited to participate through appropriate channels, contributing concerns, questions, evidence and suggestions. The implementation will demonstrate how a school can maintain a transparent, continuously updated record of its needs, decisions, actions, funding and results.

Overall: Executive Summary

Use the first 90 days of P534 – PHC School Model – Uganda to establish a locally workable country hub, beginning with willing schools in Namutumba District. Agree contributors, engage willing schools, build proportionate school baselines, put Community Assurance records into use and prepare the next investment decision.

This seed plan is a starting point for Evelyn and David, with school contributors as they become involved. Revise priorities, owners, scope, hours and milestone dates after the first participant conversations, then keep a dated decision record of changes. Named responsibilities below are proposals until accepted; school-specific facts remain to verify.

Day one is the agreed programme start, not the JSON export date. Days 1–30 cover readiness and baseline preparation, with a focused seven-day review initially targeted for days 1–7. Days 31–90 complete the two-month setup phase. Day 90 is the planned month-three funding and continuation decision; months four to six follow only under agreed scope and funding. Record any timing changes and their dependencies.

[+] Purpose

Build a practical route from locally verified school needs to accountable planning, funded action and sustainable improvement.

  • Confirm hub contributors, local relationships and willing pilot schools.
  • Establish school priorities, teaching needs, premises information and available resources through evidence and consultation.
  • Give each accepted role clear authority, manageable actions and useful records.
  • Compare proportionate responses before committing resources, and prepare the next funding decision.
  • Capture methods and learning that other schools and country hubs can assess for reuse.

Agree the initial PHC scope, funding or voluntary inputs, access and local coordination before mobilisation. Keep hub work, individual school PHC services, school operations and capital works separately scoped and budgeted.

[+] What β€œSuccess” Looks Like (by Day 90)

  • Locally reviewed hub: contributors, authority, capacity, selection criteria and revised seed documents agreed for the next stage.
  • Willing school projects: aim initially for one or two schools if interest and capacity justify it; record actual participation rather than present the target as a commitment.
  • School baselines: relevant enrolment, attendance, teaching, staffing, premises, land, WASH, assets and finances reviewed with each school's authorised leaders, with gaps visible.
  • Working assurance: named owners, usable PHC records, traceable spending and three monthly progress summaries if the programme proceeds for the full period.
  • Options and decision: proportionate improvement options with local cost evidence and a recorded proceed, revise, pause or stop recommendation.
  • Next-stage plan: a days 91–180 schedule showing resources, funding status and conditions; only the funded, authorised portion is committed.
  • Local capability and learning: contributors can update core records, explain unresolved issues and maintain an initial reusable template and learning log.

These are reviewable targets. A documented decision to narrow or defer work can be the appropriate day-90 outcome where evidence, local capacity or funding is insufficient.

Phase 1: Days 1–30 (Stabilise & Baseline)

Use the first month to agree how the hub will work, confirm local participation and organise school evidence. Evelyn and David review the seed documents together, correct local assumptions, agree their initial hub roles and capacity, and check the Namutumba school shortlist with appropriate local contacts. Identify urgent concerns promptly without assuming that any school has unsafe facilities or other conditions described in the source project.

[+] Objectives

  • Review the seed documents and agree initial roles, scope, resources, authority and the readiness decision.
  • Check school prospects and establish permissions for proportionate engagement and evidence collection.
  • Identify priority information gaps and technical or safeguarding advice needed.
  • Start simple action, concern, decision, resource and reporting routines.

[+] Actions

  • Days 1–7 – proposed hub contributors: Evelyn and David review the seed documents together, correct local assumptions, agree their initial hub roles and capacity, and check the Namutumba school shortlist with appropriate local contacts. Use the PHC readiness framework to identify dependencies, initial deliverables and a proceed, revise, pause or stop recommendation.
  • Days 1–7 – agreed hub lead and relevant school leaders: confirm authority, safe access, data permissions, safeguarding and escalation arrangements. Act promptly on any verified urgent concern, using competent help where necessary.
  • By day 14 – Evelyn, as proposed local coordinator once agreed: Evelyn checks school identities, authorised decision-makers, location and interest; introduce PHC without promising funding and record which schools wish to explore participation. Agree transparent selection criteria and a feasible initial number of schools.
  • By day 14 – willing school leaders and local coordinator: identify available pupil, attendance, grade, staffing and timetable records and arrange suitable staff, family and pupil consultation. Record sources and permissions.
  • By day 21 – local coordinator and authorised school contacts: compile available site, tenure, premises, utilities, WASH and asset information; identify missing evidence and assessments needed. Verify the local workspace, communications, travel and secure record arrangements.
  • By day 21 – finance contact to be agreed: assemble hub resources and commitments, verify the operating entity and payment route, and review relevant school finances separately. Identify who approves, pays, records and checks transactions.
  • By day 30 – David and agreed local contributors: establish the responsibility map, PHC records, practical weekly check-ins and monthly reviews; identify each school's separate project and Proposal requirements.
  • Day 30 – authorised hub and school decision-makers within their own remit: review readiness, baseline gaps, urgent actions, costs and capacity; agree or revise the setup programme and record sponsor conditions where relevant.

Reassign any unaccepted role explicitly. If school access or local coordination is unavailable, record the dependency and agree a revised scope or date instead of treating the milestone as complete.

[+] Deliverables by Day 30

  • Reviewed seed-document set and a dated change log from the first participant discussions.
  • Readiness report and recorded proceed, revise, pause or stop decision.
  • Hub responsibility map, contributor availability and initial school-engagement register showing prospects separately from participants.
  • School Baseline Pack v1 for each school assessed, with sources, permissions and dated gaps; record explicitly if no school is yet ready.
  • Initial premises and asset information and any competent-assessment brief justified by evidence.
  • Priority actions, concerns, risks and decisions with owners and next review dates.
  • Initial cost/resource schedule, transaction controls, reporting calendar and day-30 progress summary.

[+] Measures

  • The hub's agreed lead, local coordination and relevant school authorities are identified, or missing appointments are recorded with a next action.
  • The readiness recommendation and authorised decision are recorded, including any revised scope or timetable.
  • Every urgent concern and priority action has a responsible owner, next step and review date.
  • Each baseline topic has a source record, a justified not-applicable entry or an assigned evidence-gap action.
  • School interest, permission and actual participation are distinguishable in the register.
  • The day-30 summary shows completed work, resources used, spending, unresolved issues and decisions without claiming unverified outcomes.
Phase 2: Days 31–60 (Align & Standardise)

Use days 31–60 to improve the school baselines, put the shared PHC method into regular use and develop a manageable set of school-specific responses. Retain each school's authority, evidence and budget while using common templates where helpful. Match reporting effort to local capacity and protect teaching time.

[+] Objectives

  • Agree verified educational, operational and premises priorities with each participating school.
  • Make the PHC working records, activity reporting and resource controls usable by assigned contributors.
  • Shortlist proportionate options with costs, dependencies, operating implications and funding gaps.
  • Test whether the hub service adds enough practical value to justify its cost and workload.

[+] Actions

  • By day 40 – school leadership and Evelyn, as proposed local coordinator once agreed: review baseline evidence, consultation and actual pupil or classroom needs; rank priorities by learning, safety, urgency, inclusion and affordability. Record school approval and remaining uncertainties.
  • By day 45 – David and agreed PHC support: configure authorised Portal access, the seven PHC Lists, Timechunk records where appropriate and a practical offline fallback. Train only those assigned to maintain records; no analyst, administrator or trainee is appointed by this plan.
  • By day 45 – agreed finance contact and reviewer: reconcile opening balances and evidence, confirm payment authority and access, and cost the agreed roles, hours and essential resources. Keep unknown amounts marked to cost rather than zero.
  • By day 50 – local coordinator, school leaders and competent advisers where needed: verify relevant premises, land and permission requirements, access and teaching-continuity constraints before developing physical options.
  • By day 55 – school leaders and competent advisers, supported by the hub: compare no-build or operational responses, equipment, repair, rehabilitation and new construction only as relevant to the verified need. Consider useful ecological or 3D-printing research shared by Nigeria and other hubs only where it addresses a verified Ugandan school need. Check local materials, skills, permissions, logistics, operating costs and maintenance before shortlisting a method.
  • By day 60 – agreed finance, local coordination and technical contributors: collect comparable local estimates and record scope, quantities, currency, price date, exclusions, logistics, operating costs and maintenance. Distinguish estimates, quotations and commitments.
  • Day 60 – authorised hub and school leads: review the shortlist, workload, evidence quality, early funded actions and what remains necessary for the day-90 decision.

[+] Deliverables by Day 60

  • School Baseline Pack v2 and a school-reviewed priorities and requirements brief for each active pilot project, including unresolved gaps.
  • Working PHC records, hub ledger, authorised access and demonstrated participant use.
  • Prioritised school action plans with owners, dependencies, costs or costing actions and funding status.
  • Options comparison with local cost evidence, technical questions and reasons for rejecting or deferring unsuitable approaches.
  • Updated contributor and resource schedule consistent with the PHC Proposal, without inherited prices or staffing assumptions.
  • Day-60 progress summary, financial reconciliation and recorded decisions.

[+] Measures

  • Each school's authorised leaders review its brief and record the evidence behind requirements.
  • Shortlisted options use consistent comparison criteria and identify uncertainties, ongoing costs and required permissions.
  • Contributors demonstrate the records needed for their actual duties and identify any support needed.
  • Each recorded payment has approval and supporting evidence, or a visible exception with an owner and resolution date.
  • Figures in the people schedule, budgets and any forecast reconcile; unpriced items are not presented as funded or free.
  • The second monthly review records progress, workload, decisions, owners and dates.
Phase 3: Days 61–90 (Embed & Improve)

Use days 61–90 to close the most important evidence gaps, assess options and prepare a clear month-three decision. Test that local recordkeeping and review are workable, then agree the next-stage scope against actual capacity and funding. Share emerging learning without presenting research or proposed actions as completed delivery.

[+] Objectives

  • Establish a proportionate preferred route for each school assessed and identify the hub's continued role.
  • Present credible costs, resources, funding gaps, risks and remaining conditions.
  • Make reporting and local evidence updates routine without unnecessary burden.
  • Record the day-90 decision and a realistic days 91–180 plan, including pause or handover if appropriate.

[+] Actions

  • By day 70 – David, school leadership and competent advisers as needed: review options against learning priorities, inclusion, authority, land, permissions, feasibility, whole-life cost and teaching continuity. Consider a narrower service or no further investment where that is the better-supported route.
  • By day 75 – agreed finance contact and PHC support: assemble distinct hub, school-service, operating and capital budgets, with price evidence, contingency basis, funding restrictions, cash flow and gaps. Reconcile any revised Proposal tables and sponsor request.
  • By day 80 – Evelyn, as proposed local coordinator once agreed and agreed record owners: check action completion, transaction evidence, risks and indicator sources; resolve material gaps or explain their effect on the recommendation.
  • By day 80 – school leadership and local coordinator: discuss the preferred route with staff and families through suitable arrangements, and record feedback, concerns and any changes.
  • By day 85 – David and agreed local contributors: prepare the decision pack for authorised school, hub and sponsor review, showing recommendations, alternatives, costs, dependencies and decisions required.
  • By day 90 – authorised hub and school decision-makers, with sponsor agreement where funding terms require it: decide proceed, revise, pause or stop within each party's remit. Record reasons, funding conditions, further assessments, owners and review dates.
  • By day 90 – local coordinator and agreed PHC contributors: prepare the days 91–180 schedule, demonstrate routine record updates and capture the initial operating guide, reusable templates and learning log. If work pauses or ends, agree record, asset and unresolved-issue handover.

[+] Deliverables by Day 90

  • Month-three decision pack covering hub viability, school briefs, options, indicative local costs, funding gaps, risks and recommendations.
  • Recorded decisions by the authorised parties, with reasons, conditions, owners and dates.
  • Third monthly progress summary if the full period proceeds, with reconciled hub spending and visible exceptions.
  • Days 91–180 action plan showing agreed resources and funding status; only authorised, funded actions are committed.
  • Local operating guide for accepted roles, access, PHC records, approvals, reporting, safeguarding and escalation.
  • Country-hub school-assurance template v1 and initial learning log, with school-specific information and publication permissions appropriately controlled.
  • Updated seed documents and PHC Proposal reflecting participant decisions, with a pause or handover plan if continuation is not justified.

[+] Measures

  • The day-90 review records proceed, revise, pause or stop, or identifies the missing assessment, owner and dated decision point.
  • The pack clearly separates hub PHC work, school PHC services, school operations and physical works and states the evidence and uncertainty behind costs.
  • Reports cover the periods actually delivered; if all three months proceed, three summaries and their decisions are available.
  • Every continuation action has an owner, due date, resource need and funding status, with unmet conditions visible.
  • Contributors can update assigned records, explain unresolved issues and identify when escalation is needed.
  • School and beneficiary counts are verified, distinct and not duplicated across projects; activity measures are not presented as proof of educational improvement.
  • The continuation decision considers local participation, value, workload, safety, evidence and funding, rather than treating expansion or construction as automatic.